Kairos Power has picked Samsung C&T to help build a 50-megawatt nuclear reactor for Google. It plans to finish by 2030.

The deal is worth up to $100 million. It includes a $70 million investment by Samsung C&T plus engineering work provided at no extra charge, according to TechCrunch.

The work centers on Oak Ridge, Tennessee. Kairos is building two reactors there. Hermes 1 is a low-power test unit to improve the commercial design. Hermes 2 is the first full-size commercial version. Power from Hermes will supply the first 50 megawatts promised to Google.

Kairos received permission from the Nuclear Regulatory Commission to build the reactors in November 2024. It expects Hermes 2 to start running in 2030. Hermes 2 will be a fluoride salt-cooled high-temperature reactor, a type that uses very hot liquid salt to carry heat out of the core, much like coolant carries heat away from a car engine.

The Google contract dates to fall 2024. It calls for Kairos to build reactors that can make about half a gigawatt of electricity by 2035. The agreement was Google's first nuclear energy deal, as described by Google. The units are small modular reactors (SMRs), smaller reactors meant to be built in factories rather than one at a time on site, using molten-salt cooling, as reported by Bloomberg. Google plans to buy power from the reactors to meet electricity demand for AI, according to Reuters.

Samsung C&T has built or helped build about a dozen nuclear reactors around the world. Its job here is engineering support for the demonstration plant, along with money.

Kairos announced in August a separate effort on nuclear manufacturing, construction and worker training in East Tennessee. Samsung C&T Engineering & Construction Group and Cambridge Vacuum Engineering are exploring work together on NuCAMP, according to Kairos Power.

The broader context here is construction, not just physics. In nuclear, cost and schedule often depend on concrete, welding, parts supply and skilled workers. AI data centers need large amounts of steady power on a fast timeline, which puts pressure on first projects to lead quickly to repeat projects.

Looking at deployment, the setup is simple. Kairos keeps the reactor design and license work. Samsung C&T adds money and building know-how. Hermes 1 tests the design. Hermes 2 shows if it can be built and run as a business. Fifty megawatts is small for the power grid, but large enough to learn how to make parts, handle the salt, plan maintenance and run the plant.

In my view, the engineering help matters more than the $70 million. Cash buys time. Work hours from a builder with a dozen reactors behind it can help close the gap between an approved design and a finished plant on schedule, a step that has slowed new nuclear before. If Hermes 2 runs in 2030 and supplies Google, Kairos will have more than a test. It will have a working model and a trained team in East Tennessee to build from.