Belgian authorities have ordered Google to stop construction on a large datacentre in southern Belgium, because the company's requests to change its original planning permission had not been approved. The Guardian reported the order on 27 November 2026.

The building covers about three hectares of a 50-hectare business park on a former coalmine site at Aiseau-Presles, about 15 kilometres west of Charleroi. It is one of three datacentres Google originally planned for the site. Datacentres are large facilities that house computer servers, and they need substantial cooling.

The permit history is central to the dispute. Google's 2024 permit covered three smaller datacentres cooled by air. In 2025, the company applied to merge two of them into one larger facility that would use liquid cooling and draw 600 cubic metres of water per hour from the Sambre river. Wallonia's administration, the regional government covering southern Belgium, approved the amended plans in April 2026. In August, Wallonia's infrastructure minister, François Desquesnes, revoked the modified permit over drought concerns, after appeals from residents and protest groups.

Raphaël Stokis, a Walloon regional official, said inspectors who visited the site found the building almost finished, with its structural work complete even though the permit had been refused. RTBF reported that the inspectors visited on a Thursday and described the 30,000-square-metre building as enclosed at the structural stage. About 300 workers at the site received a verbal order to stop, and the order was confirmed to Google in writing.

Google has appealed the permit revocation to Belgium's Council of State, a legal body that reviews disputes over government decisions. A ruling is expected on 7 January. In a statement, Google said it was committed to maintaining an open and collaborative dialogue with the regional authorities.

Regional government spokesperson Nicolas Yernaux said a report alleging a major offence of illegal construction of a three-hectare building was being submitted to public prosecutors. Separately, Greenpeace published a report with drone footage showing that construction had continued after the permit was revoked, and it filed an emergency appeal with local planning authorities.

The Belgian case is not the only one involving Google's European datacentre plans. In October 2026, Finland opened a criminal investigation into possible breaches of environmental laws at a planned Google datacentre in rural northern Finland.